EstatePass
Contract AdminContractsmedium40% of exam part

Under Florida lien law, how long does a lienor have to file a Claim of Lien after the last day of furnishing labor or materials?

Correct Answer

B) 90 days

Florida Statute Chapter 713 requires that a Claim of Lien be filed within 90 days after the last day the lienor furnished labor or materials to the project. This is a strict deadline that cannot be extended.

Answer Options
A
180 days
B
90 days
C
60 days
D
120 days

Why This Is the Correct Answer

Florida Statute Chapter 713 explicitly establishes a 90-day deadline for filing a Claim of Lien after the last day of furnishing labor or materials. This is a mandatory statutory requirement that protects both property owners and contractors by providing a reasonable but limited timeframe for lien claims. The 90-day period is calculated from the actual last day work was performed or materials were delivered, not from contract completion or payment due dates. This deadline is strictly enforced by Florida courts and cannot be waived or extended.

Why the Other Options Are Wrong

Option C: 60 days

60 days is too short and not the statutory requirement under Florida lien law

Option D: 120 days

180 days is far beyond the statutory deadline and would result in an invalid lien claim

Memory Technique

Think '90 days = 3 months' - a full quarter year is reasonable time to file a lien claim after finishing work

Reference Hint

Florida Statutes Chapter 713 - Construction Liens, specifically Section 713.08

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.