EstatePass
Contract AdminPermitshard20% of exam part

Under Chapter 489 F.S., what is the maximum monetary limit for work that can be performed without a contractor's license?

Correct Answer

B) No monetary limit exists

Chapter 489 F.S. does not establish a monetary threshold below which contractor licensing is not required. Any person engaging in contracting work must be properly licensed, regardless of the project value, with specific exemptions for property owners and certain other limited situations.

Answer Options
A
$2,500
B
No monetary limit exists
C
$500
D
$1,000

Why This Is the Correct Answer

Chapter 489 F.S. does not establish any monetary threshold below which contractor licensing is not required. Florida law requires proper contractor licensing for any contracting work, regardless of the project's dollar value. The statute focuses on the type of work being performed rather than its cost. Only specific exemptions exist, such as property owners working on their own property or certain limited situations, but these are not based on monetary limits.

Why the Other Options Are Wrong

Option A: $2,500

$1,000 is not established as a monetary limit in Chapter 489 F.S. Florida law does not use this dollar amount as a threshold for contractor licensing requirements.

Option D: $1,000

$2,500 is not a valid monetary threshold in Chapter 489 F.S. This amount is not referenced in Florida's contractor licensing statutes as an exemption for unlicensed contracting work.

Memory Technique

Remember 'Florida = NO Money Limit' - Chapter 489 focuses on WHAT you do, not HOW MUCH it costs. Think 'Type not Price' for Florida contractor licensing.

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.