Under Chapter 489, Florida Statutes, what is the minimum experience requirement for a General Contractor license?
Correct Answer
B) 4 years of experience in the construction industry
Chapter 489 F.S. requires 4 years of experience in the construction industry for a General Contractor license. This experience must be verified and documented as part of the application process.
Why This Is the Correct Answer
Chapter 489, Florida Statutes specifically mandates that applicants for a General Contractor license must have a minimum of 4 years of experience in the construction industry. This experience requirement is clearly defined in the statute and must be properly documented and verified during the application process. The 4-year requirement ensures that contractors have sufficient practical knowledge and hands-on experience before being licensed to oversee general construction projects.
Why the Other Options Are Wrong
Option A: 2 years of experience in the construction industry
2 years is insufficient under Florida law - this falls short of the statutory requirement by 2 years and would not meet the minimum qualifications for licensure.
Option C: 5 years of experience in the construction industry
5 years exceeds the minimum requirement - while having 5 years would qualify someone, the question asks for the minimum requirement, which is 4 years.
Option D: 3 years of experience in the construction industry
3 years is one year short of the statutory minimum requirement and would not qualify an applicant for a General Contractor license.
Memory Technique
Use the mnemonic 'FOUR Foundations' - General Contractors need FOUR years of experience to build strong FOUNDATIONS for their licensing qualifications.
Reference Hint
Chapter 489, Florida Statutes - Construction Industry Licensing; also found in the Florida Building Code Study Guide under contractor licensing requirements
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Previous Question
What is the primary purpose of a performance bond in a construction contract?
Next Question
A project has an estimated direct cost of $850,000. The owner requires a 15% contingency and the contract includes liquidated damages of $1,500 per day for delays beyond the 180-day completion period. What is the total project budget including contingency?