Under California law, what is the maximum time limit for a building permit to remain valid without commencement of construction work?
Correct Answer
D) 180 days from the date of issuance
California Building Code Section 105.5 establishes that building permits expire 180 days after issuance if work has not commenced. This is a standard timeframe across California jurisdictions, though some local agencies may have shorter periods. The permit can be extended for additional 180-day periods upon request before expiration.
Why This Is the Correct Answer
California Building Code Section 105.5 (adopted from the International Building Code with California amendments) establishes that a building permit expires if work does not commence within 180 days of issuance. Note that 180 days is equivalent to 6 calendar months, making options A (18 months), C (12 months), and B (6 months expressed differently than the code language) all incorrect. The code uses '180 days' as the specific unit, not months.
Why the Other Options Are Wrong
Option A: 18 months from the date of issuance
18 months (540 days) is far beyond the 180-day statutory limit and would allow projects to stall for a year and a half without any work starting, defeating the purpose of the permit review and approval process.
Option B: 6 months from the date of issuance
While 6 months is numerically equivalent to 180 days, the California Building Code states the limit as '180 days' specifically. On the exam, option B (6 months) is a near-miss designed to catch candidates who know the approximate timeframe but not the exact code language. The legally correct answer uses the code's own terminology: 180 days.
Option C: 12 months from the date of issuance
12 months (365 days) is double the actual 180-day limit. This figure may be confused with the abandonment rule β a permit can also expire if work is abandoned or suspended for 180 days after commencement, which is a separate but related rule.
Memory Technique
Think '180 degrees = half a circle = half a year = 180 days.' A permit at the halfway point of a full year (180 days) is as far as it can go without any work starting before it expires.
More law-business Questions
Under B&P Code Section 7071.9, a contractor may deposit cash or securities instead of obtaining a surety bond. If a contractor chooses this option, where must the deposit be maintained and what happens to interest earned?
Under California's AB 5 law (Dynamex decision), which factor is NOT part of the ABC test for determining independent contractor status?
According to Business and Professions Code Section 7031, what is required when a licensed contractor supervises work performed by unlicensed employees on a construction project?
Under California Building Standards Code Title 24, which entity has the authority to issue building permits for most residential and commercial construction projects?
According to B&P Code 7159.5, service and repair contracts must include specific provisions. Which statement is correct regarding these contracts?
Which of the following activities is exempt from California contractor licensing requirements under Business and Professions Code Section 7048?
Under Cal/OSHA regulations in Title 8 CCR Section 5192, Safety Data Sheets (SDS) for hazardous chemicals used on construction sites must be readily accessible to employees during which hours?
Under California Business and Professions Code Section 7071.9, in lieu of a surety bond, what alternative security may a contractor provide to satisfy the contractor license bond requirement?
According to Cal/OSHA regulations, which of the following is NOT a required element of a written Injury and Illness Prevention Program (IIPP)?
A homeowner requests that a B-General Building Contractor provide a certificate of insurance naming the homeowner as an additional insured on the contractor's general liability policy. Under California law, what is the contractor's obligation?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
Under B&P Code 7028.15, when a California contractor submits a bid that includes both materials and labor, and the actual material costs increase by 25% after contract award due to market conditions, what is the contractor's legal obligation?
Next Question
Under California Civil Code Section 8044, which type of lien release should a contractor provide when receiving a progress payment but the work covered by the payment is not yet complete?