Under California Civil Code Section 3247, what specific lien rights does a general contractor retain when payment is not received for work performed on a construction project?
Correct Answer
B) A mechanics lien that must be recorded within 90 days of completion of work of improvement
California Civil Code Section 3247 establishes that a general contractor must record their mechanics lien within 90 days after completion of the work of improvement. This timeframe is critical for preserving lien rights and differs from the 30-day deadline that applies to subcontractors and suppliers under Civil Code Section 3248.
Why This Is the Correct Answer
California Civil Code Section 3247 grants general contractors the right to record a mechanics lien, and the deadline is 90 days after completion of the work of improvement. This 90-day window is specific to general contractors (prime contractors). Missing this deadline extinguishes the lien right entirely, so knowing the exact timeframe is essential for protecting payment.
Why the Other Options Are Wrong
Option A: A mechanics lien that must be recorded within 60 days of project completion
A 60-day recording deadline applies to subcontractors and material suppliers (Civil Code Section 3248), not to general contractors. Confusing the 60-day and 90-day deadlines is one of the most common errors on California contractor exams.
Option C: A supplier's lien that expires 120 days after final payment is due
There is no 'supplier's lien' category in California mechanics lien law with a 120-day expiration tied to final payment. California lien law uses a unified mechanics lien framework with deadlines tied to completion of work, not to when final payment was due.
Option D: A contractor's lien that remains valid for 2 years from project start
A lien that remains valid for 2 years from project start does not describe any California mechanics lien deadline. California mechanics liens must be recorded within the statutory window after completion, not from project start, and the validity of a recorded lien is governed by a separate enforcement deadline (90 days after recording to file suit).
Memory Technique
General Contractor = 90 days. Sub/Supplier = 60 days. Remember it as: generals get more time (90 > 60) because they coordinate the whole project and may not know completion has occurred as quickly as a sub who finishes a discrete scope.
More law-business Questions
Under B&P Code Section 7071.9, a contractor may deposit cash or securities instead of obtaining a surety bond. If a contractor chooses this option, where must the deposit be maintained and what happens to interest earned?
Under California's AB 5 law (Dynamex decision), which factor is NOT part of the ABC test for determining independent contractor status?
According to Business and Professions Code Section 7031, what is required when a licensed contractor supervises work performed by unlicensed employees on a construction project?
Under California Building Standards Code Title 24, which entity has the authority to issue building permits for most residential and commercial construction projects?
According to B&P Code 7159.5, service and repair contracts must include specific provisions. Which statement is correct regarding these contracts?
Which of the following activities is exempt from California contractor licensing requirements under Business and Professions Code Section 7048?
Under Cal/OSHA regulations in Title 8 CCR Section 5192, Safety Data Sheets (SDS) for hazardous chemicals used on construction sites must be readily accessible to employees during which hours?
Under California Business and Professions Code Section 7071.9, in lieu of a surety bond, what alternative security may a contractor provide to satisfy the contractor license bond requirement?
According to Cal/OSHA regulations, which of the following is NOT a required element of a written Injury and Illness Prevention Program (IIPP)?
A homeowner requests that a B-General Building Contractor provide a certificate of insurance naming the homeowner as an additional insured on the contractor's general liability policy. Under California law, what is the contractor's obligation?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
When the CSLB requires a disciplinary bond due to violations of the Contractors' License Law, what is the typical bond amount that may be imposed?
Next Question
A homeowner in California wants to cancel a home improvement contract that was signed at their residence after a door-to-door sales presentation. Under the Home Solicitation Sales Act, how long does the homeowner have to cancel the contract?