Under AIA Document A201, what is the time limit for the contractor to submit a claim for additional time or money due to a change in the work?
Correct Answer
B) 21 days after the contractor first recognizes the condition
AIA A201 requires contractors to submit claims within 21 days after the contractor first recognizes the condition giving rise to the claim or should have recognized it through reasonable diligence.
Why This Is the Correct Answer
AIA A201-2017 Section 15.1.3 requires that claims be initiated within 21 days after the claimant first recognizes the condition giving rise to the claim, or should have recognized it through reasonable diligence. Missing this deadline can waive the right to claim.
Why the Other Options Are Wrong
Option A: 30 days after substantial completion
30 days after substantial completion is incorrect and too late. Claims must be initiated promptly when the condition is first recognized, not at the end of the project. Waiting until substantial completion would waive most claims.
Option C: 60 days after final completion
60 days after final completion is incorrect and far too late. The AIA notice requirement is triggered when the contractor first recognizes the condition — which typically occurs during construction, not after completion.
Option D: 7 days after the change occurs
7 days is incorrect. While some contracts and certain notice requirements use shorter windows, the AIA A201 claim period for time and money is 21 days, not 7. Seven days might be confused with preliminary notice requirements under some state lien laws.
Memory Technique
21 days = 3 weeks. Think: you have 3 weeks (21 days) from when you SEE the problem to CLAIM it. See it → Claim it → 21 days.
More NASCLA Questions
Which AIA document contains the general conditions that govern the rights and responsibilities of all parties in a construction contract?
A construction company has direct labor costs of $85,000, direct materials of $120,000, and overhead costs of $45,000 for a project. What is the total job cost?
What is the primary purpose of job cost accounting in construction?
A construction company has current assets of $350,000 and current liabilities of $280,000. What is the company's working capital?
In CSI MasterFormat, which division covers earthwork and site preparation?
In a mechanical drawing, what does 'CFM' typically measure?
In CSI MasterFormat Division 08, which of the following would typically be included?
On a mechanical plan, what does the symbol 'RTU' typically indicate?
What is the minimum preheat temperature for welding ASTM A992 steel when the ambient temperature is 15°F?
A general contractor's balance sheet shows total assets of $850,000, current liabilities of $320,000, and long-term debt of $180,000. What is the company's equity?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Project Management
60 questions · 70% to pass
Related Study Resources
Previous Question
A time and materials contract has a labor rate of $95/hour with a 1.35 multiplier and materials at cost plus 8%. If 240 hours of labor and $18,500 in materials are used, what is the total contract amount?
Next Question
A specification calls for materials to comply with ASTM standards. Under which CSI MasterFormat division would you typically find detailed ASTM requirements for structural steel?
