Under AIA A201, what is the time limit for the architect to respond to a contractor's claim for additional time or money?
Correct Answer
C) 21 days
AIA A201 requires the architect to respond to contractor claims within 21 days of receipt. This timeframe ensures timely resolution of issues and keeps the project moving forward.
Why This Is the Correct Answer
AIA A201 requires the architect to respond to contractor claims within 21 days of receipt. This timeframe ensures timely resolution of issues and keeps the project moving forward.
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Previous Question
In a quality control program, what is the difference between quality assurance and quality control?
Next Question
During a construction coordination meeting, the electrical subcontractor reports they cannot install conduit until the structural steel is in place, but the steel contractor is delayed by 3 days. What should the general contractor do first?