Under a Guaranteed Maximum Price (GMP) contract, who bears the risk if the actual construction costs exceed the guaranteed maximum price?
Correct Answer
B) The contractor
In a GMP contract, the contractor guarantees that the project will not exceed a specified maximum price. If costs exceed this amount, the contractor absorbs the additional cost, making the contractor bear this risk.
Why This Is the Correct Answer
In a Guaranteed Maximum Price (GMP) contract, the contractor provides a contractual guarantee that the project cost will not exceed a specified maximum amount. This guarantee creates a risk transfer mechanism where the contractor assumes financial responsibility for any cost overruns beyond the GMP. The contractor is incentivized to control costs and manage the project efficiently since they must absorb any additional expenses that exceed the guaranteed maximum. This contract type protects the owner from cost escalation while placing the financial risk squarely on the contractor's shoulders.
Why the Other Options Are Wrong
Option A: The owner
The owner does not bear the risk of cost overruns in a GMP contract - that's the entire purpose of having a guaranteed maximum price. The owner's financial exposure is limited to the agreed-upon maximum amount, providing cost certainty and protection from budget overruns.
Option C: The architect
The architect is not a party to the construction contract pricing arrangements and has no financial responsibility for cost overruns. The architect's role is typically limited to design and construction administration services, not cost guarantees or financial risk assumption.
Option D: The risk is shared equally between owner and contractor
The risk is not shared equally - the fundamental principle of a GMP contract is that the contractor assumes full responsibility for costs exceeding the guaranteed maximum. While savings below the GMP might sometimes be shared, the risk of overruns is entirely the contractor's burden.
Memory Technique
Think 'GMP = Guarantee My Pocket' - the contractor is guaranteeing with their own pocket/money that costs won't exceed the maximum.
Reference Hint
Florida Building Construction Standards - Chapter on Contract Types and Risk Allocation, or Construction Law section covering GMP contract provisions
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Previous Question
To achieve LEED certification, what percentage of construction waste must be diverted from landfills?
Next Question
A dispute arises between the contractor and owner over a $25,000 change order. The contract specifies mediation before arbitration. The owner wants to proceed directly to litigation. What should happen?