Shop drawings are typically submitted by whom during the construction process?
Correct Answer
C) Specialty subcontractors or suppliers
Shop drawings are detailed drawings prepared by specialty subcontractors, fabricators, or suppliers to show how specific products or systems will be manufactured and installed. They provide more detail than the contract documents.
Why This Is the Correct Answer
Shop drawings are prepared by specialty subcontractors, fabricators, or suppliers who need to show exactly how their specific products or systems will be manufactured, detailed, and installed. These drawings translate the general design intent from the contract documents into precise fabrication and installation instructions. The subcontractors and suppliers have the specialized knowledge of their products and are responsible for ensuring their work meets the project specifications.
Why the Other Options Are Wrong
Option A: The architect
Architects create the original design drawings and contract documents, but they do not prepare shop drawings. Shop drawings are created by those who will actually fabricate and install the specific components.
Option B: The general contractor
While general contractors review and approve shop drawings as part of the submittal process, they do not typically prepare them. The GC coordinates the submittal process but relies on specialty trades to create the detailed shop drawings.
Option D: The building inspector
Building inspectors review construction for code compliance but do not prepare shop drawings. Their role is regulatory oversight, not design or fabrication documentation.
Memory Technique
Think 'SHOP = Subcontractor Has Ownership of Production' - the people making it draw it in detail
Reference Hint
Look up 'Submittals and Shop Drawings' in construction administration chapters, typically found in project management or contract administration sections
More Project Mgmt Questions
What is the minimum R-value required for wall insulation in Florida Climate Zone 2?
A subcontractor brings a new chemical product to your jobsite. Under the Globally Harmonized System (GHS), what information must be immediately available to workers?
A construction site has a trench that is 8 feet deep in Type B soil. What is the maximum allowable slope ratio for the trench walls without protective systems?
A detail drawing shows a scale of 3/4" = 1'-0". If a dimension measures 2.25 inches on the drawing, what is the actual dimension?
What is the maximum recommended spacing between drywall screws when attaching to wood studs?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Previous Question
A tower crane with a 150-foot boom is being used on a project. The load block weighs 800 pounds, and the maximum rated capacity at 100 feet radius is 4,000 pounds. What is the maximum load that can be lifted at this radius?
Next Question
Under the Globally Harmonized System (GHS), what information must be included on a Safety Data Sheet (SDS)?