EstatePass
Contract AdminProcedureseasy13% of exam part

Project documentation shows that a structural beam was relocated 2 feet north from its original design position due to a field conflict. This change was approved by the structural engineer. How should this be reflected in project closeout documents?

Correct Answer

C) Update the as-built drawings to show actual location

Approved field changes must be reflected in as-built drawings to show the actual constructed conditions. This ensures future maintenance and renovation work has accurate information.

Answer Options
A
Note the change in the project diary only
B
Include only in the change order log
C
Update the as-built drawings to show actual location
D
Document in meeting minutes but not on drawings

Why This Is the Correct Answer

As-built drawings are the official record of how the project was actually constructed, not how it was originally designed. When approved field changes occur, such as relocating a structural beam, these modifications must be documented in the as-built drawings to reflect the true constructed conditions. This ensures that future maintenance, renovations, or emergency work will have accurate information about the actual location of structural elements. As-built drawings are a critical component of project closeout documentation and serve as the permanent record for the facility owner.

Why the Other Options Are Wrong

Option B: Include only in the change order log

While project diaries are important for daily documentation, they are not sufficient for recording permanent changes to the constructed work. Project diaries are typically temporary records used during construction, whereas structural changes need to be permanently documented in drawings that will be used for future reference.

Option D: Document in meeting minutes but not on drawings

Meeting minutes document discussions and decisions but do not provide the precise technical information needed for future work. Like change order logs, meeting minutes are administrative records that supplement but cannot replace the technical accuracy required in as-built drawings.

Memory Technique

Think 'AS-BUILT = AS-ACTUALLY-BUILT' - if it changed in the field, it must change on the as-built drawings

Reference Hint

Florida Building Code - Chapter 1, Section 107 (Submittal Documents) and AIA Document A201 - General Conditions, Article 3.11 (As-Built Documents)

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.