EstatePass
Contract AdminProcedureseasy13% of exam part

Project documentation shows that a structural beam was relocated 2 feet north from its original design position due to a field conflict. This change was approved by the structural engineer. How should this be reflected in project closeout documents?

Correct Answer

B) Update the as-built drawings to show actual location

Approved field changes must be reflected in as-built drawings to show the actual constructed conditions. This ensures future maintenance and renovation work has accurate information.

Answer Options
A
Note the change in the project diary only
B
Update the as-built drawings to show actual location
C
Include only in the change order log
D
Document in meeting minutes but not on drawings

Why This Is the Correct Answer

As-built drawings are the official record of how the project was actually constructed, not how it was originally designed. When approved field changes occur, such as relocating a structural beam, these modifications must be documented in the as-built drawings to reflect the true constructed conditions. This ensures that future maintenance, renovations, or emergency work will have accurate information about the actual location of structural elements. As-built drawings are a critical component of project closeout documentation and serve as the permanent record for the facility owner.

Why the Other Options Are Wrong

Option A: Note the change in the project diary only

While project diaries are important for daily documentation, they are not sufficient for recording permanent changes to the constructed work. Project diaries are typically temporary records used during construction, whereas structural changes need to be permanently documented in drawings that will be used for future reference.

Option C: Include only in the change order log

Change order logs track the administrative and financial aspects of changes but do not provide the technical details of actual constructed conditions. While the change should be included in the change order log, this alone is insufficient - the actual location must be shown graphically in the as-built drawings.

Option D: Document in meeting minutes but not on drawings

Meeting minutes document discussions and decisions but do not provide the precise technical information needed for future work. Like change order logs, meeting minutes are administrative records that supplement but cannot replace the technical accuracy required in as-built drawings.

Memory Technique

Think 'AS-BUILT = AS-ACTUALLY-BUILT' - if it changed in the field, it must change on the as-built drawings

Reference Hint

Florida Building Code - Chapter 1, Section 107 (Submittal Documents) and AIA Document A201 - General Conditions, Article 3.11 (As-Built Documents)

More Contract Admin Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing