EstatePass
Contract AdminContractsmedium40% of exam part

In Florida, when must a Notice to Owner be served on a private construction project?

Correct Answer

A) No later than 45 days from first furnishing labor or materials

Florida Statute 713.06 requires that a Notice to Owner must be served no later than 45 days from the date the lienor first furnishes labor, services, or materials to the project. This notice is a prerequisite to lien rights.

Answer Options
A
No later than 45 days from first furnishing labor or materials
B
Within 15 days of first furnishing labor or materials
C
Before starting any work on the project
D
Within 90 days of project completion

Why This Is the Correct Answer

Florida Statute 713.06 establishes that a Notice to Owner must be served no later than 45 days from the date the lienor first furnishes labor, services, or materials to the project. This 45-day deadline is critical for preserving lien rights on private construction projects. The notice serves to inform the property owner of potential lien claimants and is a mandatory prerequisite for filing a valid construction lien in Florida.

Why the Other Options Are Wrong

Option B: Within 15 days of first furnishing labor or materials

The 15-day timeframe is incorrect for Notice to Owner requirements. While some construction-related notices in Florida have 15-day deadlines, the Notice to Owner specifically requires service within 45 days of first furnishing labor or materials. Confusing this with other notice periods could result in loss of lien rights.

Option C: Before starting any work on the project

Serving the Notice to Owner before starting work is not required by Florida law. The statute allows up to 45 days from first furnishing labor or materials, meaning the notice can be served after work begins. Requiring notice before work starts would be unnecessarily restrictive and impractical for many contractors and suppliers.

Option D: Within 90 days of project completion

The 90-day period after project completion is far too late and relates to different lien deadlines, not the Notice to Owner requirement. By this time, the opportunity to serve a valid Notice to Owner would have long passed, potentially eliminating lien rights entirely under Florida Statute 713.06.

Memory Technique

Remember '45 Days to Notify' - the Notice to Owner must be served within 45 days of first furnishing labor or materials to preserve your lien rights in Florida.

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.