EstatePass
Contract AdminContractseasy40% of exam part

In Florida, how long does a lienor have to file a Claim of Lien after the final furnishing of labor or materials?

Correct Answer

C) 90 days

Under Florida Statute 713.08, a Claim of Lien must be filed within 90 days after the final furnishing of labor, services, or materials by the lienor.

Answer Options
A
45 days
B
60 days
C
90 days
D
120 days

Why This Is the Correct Answer

Florida Statute 713.08 specifically establishes that a Claim of Lien must be filed within 90 days after the final furnishing of labor, services, or materials by the lienor. This 90-day period is a strict statutory deadline that cannot be extended. The statute is designed to provide a reasonable timeframe for lienors to perfect their lien rights while also providing certainty to property owners about when potential lien claims must be filed. Missing this 90-day deadline results in the complete loss of lien rights.

Why the Other Options Are Wrong

Option A: 45 days

45 days is too short and not the statutory requirement under Florida law

Option B: 60 days

60 days is insufficient time under Florida Statute 713.08

Option D: 120 days

120 days exceeds the statutory deadline and would be too late to file a valid lien claim

Memory Technique

Think '90 days = 3 months' - a full quarter of the year to file your lien claim, which seems like a reasonable middle ground between too short and too long

Reference Hint

Florida Statutes Chapter 713 - Construction Liens, specifically Section 713.08

More Contract Admin Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing