In CPM scheduling, what is total float (slack)?
Correct Answer
A) The amount of time an activity can be delayed without delaying the project
Total float is the amount of time an activity can be delayed without delaying the overall project completion date. Activities on the critical path have zero total float.
Why This Is the Correct Answer
Total float (also called total slack) is indeed the amount of time an activity can be delayed without affecting the project's completion date. This is calculated as Late Start minus Early Start (or Late Finish minus Early Finish). Activities with zero total float are on the critical path, meaning any delay to these activities will delay the entire project. Understanding total float is crucial for project managers to identify which activities have scheduling flexibility.
Why the Other Options Are Wrong
Option B: The shortest duration possible for an activity
This describes the optimistic duration or crash duration of an activity, not total float. The shortest possible duration is a time estimate used in activity duration analysis, but has nothing to do with scheduling flexibility or slack time.
Option C: The buffer time added to each activity for safety
This describes contingency time or buffer time, which is deliberately added time for risk management. Total float is not intentionally added - it's a calculated value that shows natural scheduling flexibility based on the network logic and activity relationships.
Option D: The time between the early start and late start of an activity
While this calculation (Late Start - Early Start) does equal total float, this answer describes the calculation method rather than defining what total float actually represents. The definition should focus on the concept of delay tolerance, not just the mathematical relationship.
Memory Technique
Think 'FLOAT = FLEXIBILITY'. Total float tells you how much an activity can 'float' in the schedule without sinking the project deadline.
Reference Hint
Look up 'Critical Path Method (CPM)' and 'Project Scheduling' in construction management references, typically found in project management chapters or PMBOK Guide sections on schedule management.
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Previous Question
A framing crew of 4 carpenters can frame 1,200 square feet per day. If carpenters earn $28 per hour for an 8-hour day, what is the labor cost per square foot for framing?
Next Question
A painting crew can cover 2,000 square feet per day at $0.85 per square foot. For a building with 25,000 square feet of wall area, what is the total estimated painting cost?