EstatePass
Business & FinanceOperationseasy10% of exam part

In CPM scheduling, what happens to the project duration when an activity on the critical path is delayed?

Correct Answer

B) Project duration increases by the same amount as the delay

Activities on the critical path have zero float, so any delay in a critical path activity directly increases the project duration by the same amount. This is why critical path activities require careful monitoring.

Answer Options
A
Project duration remains unchanged
B
Project duration increases by the same amount as the delay
C
Project duration may increase depending on other activities
D
Project duration decreases due to schedule compression

Why This Is the Correct Answer

Activities on the critical path have zero float (slack time), meaning there is no buffer time available to absorb delays. When any activity on the critical path is delayed, that delay directly extends the overall project completion date. Since the critical path determines the minimum project duration, any delay to critical path activities automatically increases the total project duration by exactly the same amount as the delay.

Why the Other Options Are Wrong

Option A: Project duration remains unchanged

This is incorrect because critical path activities have no float to absorb delays. Any delay to a critical path activity must extend the project duration since these activities determine the longest path through the project network.

Option C: Project duration may increase depending on other activities

This is incorrect because critical path activities always affect project duration when delayed. There is no 'may increase' scenario - delays to critical path activities will always increase project duration by the exact amount of the delay.

Option D: Project duration decreases due to schedule compression

This is incorrect because delays cannot cause schedule compression or duration decreases. A delay by definition extends time, and critical path delays specifically extend the overall project duration.

Memory Technique

Think 'Critical = No Cushion' - critical path activities have no time cushion (float), so any delay hits the project finish date directly, like a domino effect with no buffer to stop it.

Reference Hint

Look up CPM (Critical Path Method) scheduling in the project management or scheduling chapter of your contractor reference manual, specifically the section on float/slack calculations.

More Business & Finance Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing