EstatePass
Business & FinanceOperationsmedium10% of exam part

In CPM scheduling, if an activity has an Early Start of day 10, duration of 5 days, and Late Finish of day 18, what is the total float?

Correct Answer

D) 3 days

Total float = Late Finish - Early Start - Duration = 18 - 10 - 5 = 3 days. This activity can be delayed up to 3 days without affecting the project completion date.

Answer Options
A
8 days
B
5 days
C
0 days
D
3 days

Why This Is the Correct Answer

Total float represents the amount of time an activity can be delayed without affecting the project's critical path. The formula is Total Float = Late Finish - Early Start - Duration. Using the given values: 18 - 10 - 5 = 3 days. This means the activity has 3 days of flexibility before it impacts the overall project schedule.

Why the Other Options Are Wrong

Option A: 8 days

5 days incorrectly assumes the duration equals the float, but float is the difference between available time window and required duration.

Option B: 5 days

Zero days would indicate this is a critical path activity with no float, but the calculation shows 3 days of available delay time.

Memory Technique

Remember 'LF-ES-D' as 'Late Finish minus Early Start minus Duration' or think 'time window minus work time equals free time.'

Reference Hint

Project Management chapter covering Critical Path Method (CPM) and scheduling calculations, typically found in construction management or project scheduling sections.

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.