EstatePass
Business & FinanceOperationsmedium10% of exam part

In CPM scheduling, if an activity has an Early Start of day 10, duration of 5 days, and Late Finish of day 20, what is the activity's total float?

Correct Answer

B) 5 days

Total float = Late Finish - Early Start - Duration = 20 - 10 - 5 = 5 days. This represents how many days the activity can be delayed without affecting the project completion date.

Answer Options
A
0 days
B
5 days
C
10 days
D
15 days

Why This Is the Correct Answer

Option B is correct because total float is calculated using the formula: Late Finish - Early Start - Duration. With the given values (LF=20, ES=10, Duration=5), the calculation yields 20 - 10 - 5 = 5 days. This means the activity can be delayed up to 5 days without impacting the project's critical path or overall completion date. Total float represents the scheduling flexibility available for non-critical activities.

Why the Other Options Are Wrong

Option A: 0 days

Option A is incorrect because 0 days would indicate this is a critical path activity with no scheduling flexibility, but the calculation clearly shows 5 days of float available.

Option C: 10 days

Option C is incorrect because 10 days appears to be confusing the Early Start date with the actual float calculation, ignoring the duration component of the formula.

Option D: 15 days

Option D is incorrect because 15 days seems to be adding the duration to the Early Start (10 + 5) rather than properly applying the total float formula.

Memory Technique

Remember 'LED' for the total float formula: Late finish minus Early start minus Duration (LF - ES - D = Total Float)

Reference Hint

Look up CPM scheduling and float calculations in the project management or scheduling chapter of your contractor reference manual, typically found under 'Critical Path Method' or 'Network Analysis'.

More Business & Finance Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing