In CPM scheduling, if an activity has an Early Start of day 10, duration of 5 days, and Late Finish of day 20, what is the activity's total float?
Correct Answer
B) 5 days
Total float = Late Finish - Early Start - Duration = 20 - 10 - 5 = 5 days. This represents how many days the activity can be delayed without affecting the project completion date.
Why This Is the Correct Answer
Option B is correct because total float is calculated using the formula: Late Finish - Early Start - Duration. With the given values (LF=20, ES=10, Duration=5), the calculation yields 20 - 10 - 5 = 5 days. This means the activity can be delayed up to 5 days without impacting the project's critical path or overall completion date. Total float represents the scheduling flexibility available for non-critical activities.
Why the Other Options Are Wrong
Option A: 0 days
Option A is incorrect because 0 days would indicate this is a critical path activity with no scheduling flexibility, but the calculation clearly shows 5 days of float available.
Option C: 10 days
Option C is incorrect because 10 days appears to be confusing the Early Start date with the actual float calculation, ignoring the duration component of the formula.
Option D: 15 days
Option D is incorrect because 15 days seems to be adding the duration to the Early Start (10 + 5) rather than properly applying the total float formula.
Memory Technique
Remember 'LED' for the total float formula: Late finish minus Early start minus Duration (LF - ES - D = Total Float)
Reference Hint
Look up CPM scheduling and float calculations in the project management or scheduling chapter of your contractor reference manual, typically found under 'Critical Path Method' or 'Network Analysis'.
More Business & Finance Questions
A contractor's license expires on March 31st. If they submit a renewal application on April 15th, what additional requirement must be met under Florida regulations?
A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?
In Florida, what is the minimum workers' compensation insurance coverage required for construction companies with employees?
What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?
A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?