In CPM scheduling, if an activity has a total float of 5 days and free float of 2 days, what happens if this activity is delayed by 3 days?
Correct Answer
B) The next activity will be delayed by 1 day
With 2 days of free float, a 3-day delay will consume the free float and delay the next activity by 1 day (3-2=1). The project completion won't be affected since total float exceeds the delay.
Why This Is the Correct Answer
Free float represents the maximum delay an activity can experience without affecting the start of its immediate successor activities. Since this activity has 2 days of free float and is delayed by 3 days, the free float absorbs 2 days of the delay, leaving 1 day that will push back the start of the next activity. The total float of 5 days is greater than the 3-day delay, so the project's critical path and completion date remain unaffected.
Why the Other Options Are Wrong
Option A: The project completion date will be delayed by 3 days
The project completion date will not be delayed because the total float (5 days) is greater than the delay (3 days). Total float represents the maximum delay an activity can experience without affecting the project completion date.
Option C: The project remains on schedule
The project schedule is affected because the 3-day delay exceeds the 2-day free float, meaning the next activity will be delayed by 1 day even though the overall project completion remains on schedule.
Option D: All subsequent activities will be delayed by 3 days
Not all subsequent activities will be delayed by the full 3 days. Only 1 day of delay (3 days minus 2 days of free float) will affect the next activity, and subsequent activities may have their own float to absorb delays.
Memory Technique
FREE float = affects the NEXT activity FREE of charge. Total float = affects the TOTAL project. Formula: Next Activity Delay = Activity Delay - Free Float (if positive)
Reference Hint
Look up CPM scheduling, float calculations, and activity relationships in the project management or scheduling chapter of your contractor reference manual
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Previous Question
A contractor owns a bulldozer that cost $180,000 new, has a useful life of 8 years, and an estimated salvage value of $36,000. Using straight-line depreciation, what is the hourly ownership cost if the machine operates 1,500 hours per year?
Next Question
During a safety meeting, a worker reports that the required fall protection equipment is uncomfortable and requests to work without it on a low-risk task. How should the supervisor respond?