In AIA Document A401, which party is primarily responsible for coordinating the work of sub-subcontractors?

Correct Answer

C) The subcontractor

Under AIA A401, the subcontractor is responsible for coordinating and supervising their own sub-subcontractors' work.

Answer Options
A
The owner
B
The general contractor
C
The subcontractor
D
The architect

Why This Is the Correct Answer

Under AIA A401, the subcontractor is responsible for coordinating and supervising their own sub-subcontractors' work.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.