EstatePass
Contract AdminProceduresmedium13% of exam part

In a three-point quality control inspection system, who typically performs the final inspection before work acceptance?

Correct Answer

A) The owner's representative or independent inspector

In a three-point system, the subcontractor performs self-inspection, the general contractor performs oversight inspection, and the owner's representative or independent inspector performs final acceptance inspection.

Answer Options
A
The owner's representative or independent inspector
B
The installing subcontractor only
C
The general contractor's quality control manager
D
The material supplier

Why This Is the Correct Answer

In a three-point quality control inspection system, the owner's representative or independent inspector performs the final inspection because they provide an unbiased, third-party verification that work meets contract specifications. This creates a checks-and-balances system where the party paying for the work has independent verification of quality before accepting and paying for completed work. The owner's representative has the authority to accept or reject work on behalf of the owner, making them the logical choice for final acceptance inspection.

Why the Other Options Are Wrong

Option B: The installing subcontractor only

The installing subcontractor only performs the first point of inspection (self-inspection) in the three-point system. They cannot perform final acceptance inspection because they have a financial interest in having their work accepted, creating a conflict of interest.

Option C: The general contractor's quality control manager

Material suppliers are not part of the three-point inspection system. Their role is limited to providing materials that meet specifications, not performing quality control inspections of installed work.

Option D: The material supplier

The general contractor's quality control manager performs the second point of inspection (oversight inspection) in the three-point system. While they provide important quality oversight, they still represent the contractor's interests and cannot provide the independent final acceptance that the owner requires.

Memory Technique

Think 'SGO' - Subcontractor (self-inspection), General contractor (oversight), Owner's rep (final acceptance). The person writing the checks gets the final say!

Reference Hint

Florida Building Code, Chapter 1 - Administration and Enforcement, Section on Inspections; also check project management sections in contractor reference materials

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.