In a three-point quality control inspection system, who typically performs the final inspection before work acceptance?
Correct Answer
C) The owner's representative or independent inspector
In a three-point system, the subcontractor performs self-inspection, the general contractor performs oversight inspection, and the owner's representative or independent inspector performs final acceptance inspection.
Why This Is the Correct Answer
In a three-point quality control inspection system, the owner's representative or independent inspector performs the final inspection because they provide an unbiased, third-party verification that work meets contract specifications. This creates a checks-and-balances system where the party paying for the work has independent verification of quality before accepting and paying for completed work. The owner's representative has the authority to accept or reject work on behalf of the owner, making them the logical choice for final acceptance inspection.
Why the Other Options Are Wrong
Option A: The installing subcontractor only
The installing subcontractor only performs the first point of inspection (self-inspection) in the three-point system. They cannot perform final acceptance inspection because they have a financial interest in having their work accepted, creating a conflict of interest.
Option B: The general contractor's quality control manager
The general contractor's quality control manager performs the second point of inspection (oversight inspection) in the three-point system. While they provide important quality oversight, they still represent the contractor's interests and cannot provide the independent final acceptance that the owner requires.
Option D: The material supplier
Material suppliers are not part of the three-point inspection system. Their role is limited to providing materials that meet specifications, not performing quality control inspections of installed work.
Memory Technique
Think 'SGO' - Subcontractor (self-inspection), General contractor (oversight), Owner's rep (final acceptance). The person writing the checks gets the final say!
Reference Hint
Florida Building Code, Chapter 1 - Administration and Enforcement, Section on Inspections; also check project management sections in contractor reference materials
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass