EstatePass
Contract AdminContractseasy40% of exam part

In a lump sum contract, what is the primary risk assumed by the general contractor?

Correct Answer

A) Material price fluctuations and cost overruns

In a lump sum contract, the contractor agrees to complete the work for a fixed price, assuming the risk of cost overruns, material price increases, and other unforeseen expenses. The contractor must absorb these costs unless covered by change orders.

Answer Options
A
Material price fluctuations and cost overruns
B
Owner's ability to pay
C
Weather delays only
D
Subcontractor performance only

Why This Is the Correct Answer

In a lump sum contract, the contractor agrees to complete the project for a fixed price regardless of actual costs incurred. This means the contractor bears the financial risk if materials become more expensive, labor costs increase, or unexpected expenses arise during construction. The contractor cannot pass these additional costs to the owner unless there are approved change orders for scope changes. This risk-reward structure is the fundamental characteristic that distinguishes lump sum contracts from cost-plus contracts.

Why the Other Options Are Wrong

Option B: Owner's ability to pay

While the owner's ability to pay is always a concern, this is not the primary risk specific to lump sum contracts. Payment risk exists in all contract types and is typically addressed through payment bonds, lien rights, and credit checks during the bidding process.

Option C: Weather delays only

Weather delays are just one type of risk among many that contractors face in lump sum contracts. The primary risk encompasses all cost overruns, including but not limited to weather-related delays, material price increases, labor cost fluctuations, and unforeseen conditions.

Option D: Subcontractor performance only

Subcontractor performance is only one component of the overall cost risk in lump sum contracts. While poor subcontractor performance can lead to cost overruns, the primary risk includes all potential cost increases including materials, labor, equipment, and other project expenses.

Memory Technique

Think 'LUMP SUM LUMPS ALL RISKS ON CONTRACTOR' - the fixed price means the contractor absorbs all cost increases that aren't covered by change orders.

Reference Hint

Florida Building Construction Standards - Chapter on Contract Types and Risk Allocation, or Construction Law section covering contract delivery methods

More Contract Admin Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing