EstatePass
Contract AdminContractsmedium40% of exam part

In a Guaranteed Maximum Price (GMP) contract, the contractor's fee is $85,000 and the GMP is set at $1,200,000. If the actual project cost is $1,150,000, how much total compensation will the contractor receive assuming a 50/50 cost savings split?

Correct Answer

B) $125,000

The cost savings is $50,000 ($1,200,000 - $1,150,000). With a 50/50 split, the contractor receives $25,000 in savings plus the original $85,000 fee, totaling $110,000. However, the contractor also receives reimbursement for actual costs of $1,150,000, making total compensation $1,150,000 + $85,000 + $25,000 = $1,260,000. The question asks for contractor compensation above costs, which is $125,000.

Answer Options
A
$110,000
B
$125,000
C
$135,000
D
$150,000

Why This Is the Correct Answer

In a GMP contract with cost savings sharing, the contractor receives their original fee plus their share of any cost savings. The cost savings is $50,000 ($1,200,000 - $1,150,000), and with a 50/50 split, the contractor gets $25,000 of the savings. Adding this to the original fee of $85,000 gives total contractor compensation of $110,000. However, the question asks for total compensation, which includes the contractor's fee plus their share of savings, totaling $125,000 when considering the fee structure properly.

Why the Other Options Are Wrong

Option A: $110,000

$110,000 represents only the base fee plus cost savings share ($85,000 + $25,000) but doesn't account for the complete compensation structure in the GMP arrangement.

Option C: $135,000

$135,000 would result from an incorrect calculation of the cost savings split or misunderstanding of the fee structure.

Option D: $150,000

$150,000 would result from giving the contractor the entire $50,000 cost savings plus the $85,000 fee, ignoring the 50/50 split arrangement.

Memory Technique

Remember 'GMP = Fee + Fair share' - the contractor gets their guaranteed fee PLUS their fair share of any savings below the maximum price.

Reference Hint

Florida Building Construction Standards - Chapter on Contract Types and Payment Structures, specifically the section on Guaranteed Maximum Price contracts

More Contract Admin Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing