EstatePass
NASCLAProject Mgmteasy22% of exam part

In a Critical Path Method (CPM) schedule, Activity A has a duration of 5 days, Activity B has a duration of 8 days, and Activity C has a duration of 3 days. Activities A and B can start simultaneously, and Activity C cannot start until both A and B are complete. What is the total project duration?

Correct Answer

D) 11 days

Since A (5 days) and B (8 days) run concurrently, the longest path is B at 8 days. Activity C (3 days) starts after both are complete, so total duration is 8 + 3 = 11 days.

Answer Options
A
13 days
B
8 days
C
16 days
D
11 days

Why This Is the Correct Answer

In CPM scheduling, when activities run concurrently, the critical path is determined by the longest duration activity. Activities A (5 days) and B (8 days) start simultaneously, so B becomes the controlling factor at 8 days. Activity C (3 days) cannot begin until both A and B finish, creating a sequential relationship. Therefore, the total project duration is 8 days (longest concurrent path) + 3 days (sequential activity C) = 11 days.

Why the Other Options Are Wrong

Option A: 13 days

This incorrectly adds all three activity durations (5 + 8 + 3 = 16 days) as if they were sequential. However, Activities A and B run concurrently, not one after the other, so their durations should not be added together.

Option B: 8 days

This only accounts for Activity B's duration (8 days) and ignores Activity C entirely. While B is the longest concurrent activity, C must still be completed after both A and B finish, adding 3 more days to the total.

Option C: 16 days

This adds Activities A and B sequentially (5 + 8 = 13 days) then adds C (13 + 3 = 16 days). This is incorrect because A and B run simultaneously, not consecutively, so only the longer duration (8 days) should be used.

Memory Technique

Remember 'Concurrent = MAX, Sequential = ADD' - when activities run at the same time, take the maximum duration; when they follow each other, add the durations.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.