In a cost-plus-fee contract, what is the contractor's primary obligation regarding project costs?
Correct Answer
B) To provide detailed documentation and accounting of all reimbursable costs
In cost-plus contracts, the contractor must maintain detailed records and provide transparent accounting of all costs since the owner reimburses actual costs plus a fee. This documentation is essential for payment and audit purposes.
Why This Is the Correct Answer
In cost-plus-fee contracts, the contractor is reimbursed for actual project costs plus a predetermined fee. Since the owner pays for actual costs rather than a fixed price, the contractor has a legal and contractual obligation to maintain meticulous records of all expenses. This documentation serves as proof of legitimate costs and enables proper reimbursement. Without detailed accounting, the owner cannot verify costs and the contractor cannot receive proper payment.
Why the Other Options Are Wrong
Option A: To guarantee a maximum project cost
Cost-plus contracts do not require contractors to guarantee maximum costs - that would be a guaranteed maximum price (GMP) contract. In pure cost-plus arrangements, costs can vary and the owner bears the risk of cost overruns.
Option C: To absorb any cost overruns beyond the original estimate
In cost-plus contracts, the owner, not the contractor, typically absorbs cost overruns since they reimburse actual costs. The contractor is protected from cost risk, which is why detailed documentation is so crucial for reimbursement.
Option D: To share cost savings equally with the owner
Cost savings sharing is not a standard feature of basic cost-plus contracts. This might occur in cost-plus contracts with incentive clauses, but it's not the contractor's primary obligation regarding project costs.
Memory Technique
Think 'Cost-Plus = Paperwork Plus' - the contractor gets reimbursed PLUS a fee, but only with detailed paperwork to back up every cost
Reference Hint
Construction Contract Administration chapter or Project Delivery Methods section covering cost-plus contract types
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Previous Question
What is the primary advantage of using historical cost data in estimating?
Next Question
A masonry crew can lay 400 square feet of block wall per day. If the project requires 3,200 square feet of block work and the crew costs $1,800 per day, what is the total labor cost for this work?