Correct Answer

B) 90 days

California Civil Code Section 3116 establishes that subcontractors must file their mechanic's lien within 90 days after completion of their work of improvement. This is different from the general contractor's deadline and is a critical timeline for project managers to communicate to subcontractors for proper lien management.

Answer Options
A
30 days
B
90 days
C
120 days
D
60 days

Why This Is the Correct Answer

Under California Civil Code Section 3116, subcontractors have exactly 90 days after completion of their work of improvement to file a mechanic's lien. This 90-day deadline is specifically established for subcontractors and differs from other parties' filing deadlines. The timeline begins when the subcontractor completes their portion of work, not when the entire project is finished. This is a critical deadline that project managers must track and communicate to ensure proper lien rights are preserved.

Why the Other Options Are Wrong

Option A: 30 days

30 days is too short and not the statutory requirement. This timeframe might be confused with preliminary notice deadlines or other construction-related notice periods, but it does not apply to mechanic's lien filing deadlines for subcontractors under California law.

Option C: 120 days

120 days exceeds the statutory deadline and would result in loss of lien rights. While some states may have longer periods, California specifically requires subcontractors to file within 90 days. Waiting 120 days would make the lien invalid and unenforceable.

Option D: 60 days

60 days is insufficient under California Civil Code Section 3116. This shorter timeframe might be confused with other construction notice requirements or deadlines in other jurisdictions, but California law specifically provides subcontractors with 90 days to file their mechanic's liens.

Memory Technique

Remember '90 days for Subs' - subcontractors get 90 days to file their mechanic's lien after completing their work portion.

Was this explanation helpful?

More law-business Questions

Under B&P Code Section 7071.9, a contractor may deposit cash or securities instead of obtaining a surety bond. If a contractor chooses this option, where must the deposit be maintained and what happens to interest earned?

Under California's AB 5 law (Dynamex decision), which factor is NOT part of the ABC test for determining independent contractor status?

According to Business and Professions Code Section 7031, what is required when a licensed contractor supervises work performed by unlicensed employees on a construction project?

Under California Building Standards Code Title 24, which entity has the authority to issue building permits for most residential and commercial construction projects?

According to B&P Code 7159.5, service and repair contracts must include specific provisions. Which statement is correct regarding these contracts?

Which of the following activities is exempt from California contractor licensing requirements under Business and Professions Code Section 7048?

Under Cal/OSHA regulations in Title 8 CCR Section 5192, Safety Data Sheets (SDS) for hazardous chemicals used on construction sites must be readily accessible to employees during which hours?

Under California Business and Professions Code Section 7071.9, in lieu of a surety bond, what alternative security may a contractor provide to satisfy the contractor license bond requirement?

According to Cal/OSHA regulations, which of the following is NOT a required element of a written Injury and Illness Prevention Program (IIPP)?

A homeowner requests that a B-General Building Contractor provide a certificate of insurance naming the homeowner as an additional insured on the contractor's general liability policy. Under California law, what is the contractor's obligation?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.