EstatePass
Contract AdminProcedureshard13% of exam part

For LEED certification, what percentage of a building's energy use must be offset to achieve net-zero energy performance?

Correct Answer

B) 100%

Net-zero energy performance requires that 100% of the building's energy use be offset by on-site renewable energy production or other approved methods, meaning the building produces as much energy as it consumes annually.

Answer Options
A
75%
B
100%
C
90%
D
110%

Why This Is the Correct Answer

Net-zero energy performance in LEED certification requires 100% of a building's annual energy consumption to be offset by on-site renewable energy production or other approved methods. This means the building must produce as much clean energy as it consumes over a 12-month period, achieving a perfect energy balance. The 100% threshold is the defining characteristic that distinguishes net-zero from other high-performance energy standards.

Why the Other Options Are Wrong

Option A: 75%

75% offset would represent a high-performance building but falls short of net-zero standards. This level might qualify for other LEED energy credits but does not meet the complete energy independence required for net-zero certification, leaving 25% of energy needs unmet by renewable sources.

Option C: 90%

90% offset represents excellent energy performance but still falls 10% short of net-zero requirements. While this would earn significant LEED points for energy efficiency, it does not achieve the complete energy balance necessary for true net-zero certification under LEED standards.

Option D: 110%

110% would exceed net-zero requirements, creating a net-positive energy building that produces more energy than it consumes. While environmentally beneficial, this exceeds the minimum 100% threshold needed for net-zero certification and represents a higher performance level than required.

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.