EstatePass
Contract AdminProceduresmedium13% of exam part

For a LEED project, which of the following strategies would contribute to earning points in the Water Efficiency category?

Correct Answer

D) Using low-flow plumbing fixtures and native landscaping

Water Efficiency points in LEED are earned through strategies that reduce water consumption, such as low-flow plumbing fixtures and native landscaping that requires minimal irrigation.

Answer Options
A
Installing high-efficiency lighting systems
B
Improving indoor air quality with low-VOC materials
C
Purchasing materials from local suppliers
D
Using low-flow plumbing fixtures and native landscaping

Why This Is the Correct Answer

Option B is correct because the LEED Water Efficiency category specifically focuses on reducing water consumption and managing water resources effectively. Low-flow plumbing fixtures directly reduce indoor water usage, while native landscaping reduces or eliminates the need for irrigation since these plants are adapted to local climate conditions. Both strategies directly contribute to water conservation goals and can earn points in the Water Efficiency category.

Why the Other Options Are Wrong

Option A: Installing high-efficiency lighting systems

Purchasing materials from local suppliers contributes to the Materials and Resources category by reducing transportation impacts and supporting the local economy, not water efficiency.

Option C: Purchasing materials from local suppliers

High-efficiency lighting systems contribute to the Energy and Atmosphere category, not Water Efficiency, as they focus on reducing electrical energy consumption rather than water usage.

Memory Technique

Use the acronym 'WEIM-ST' for LEED categories: Water, Energy, Indoor, Materials, Sites, Transportation. Match water-saving strategies only to the Water category.

Reference Hint

Florida Building Code Chapter 4 - Special Detailed Requirements Based on Use and Occupancy, Green Building Standards section

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.