For a $2.8 million commercial construction project in Florida, what is the typical range for a construction contingency allowance?
Correct Answer
D) 5% to 10%
Construction contingencies typically range from 5% to 10% of the project cost, depending on project complexity, design completeness, and risk factors.
Why This Is the Correct Answer
Construction contingency allowances of 5% to 10% are industry standard for commercial projects like this $2.8 million facility. This range accounts for unforeseen conditions, design changes, and material price fluctuations that commonly occur during construction. The percentage is based on project complexity, with simpler projects toward the lower end and more complex projects toward the higher end. This range balances adequate risk coverage without excessive cost padding.
Why the Other Options Are Wrong
Option B: 12% to 15%
12% to 15% is excessive for a standard commercial construction project and would indicate either extremely high-risk conditions or poor project planning. Such high contingencies are typically only used for highly complex projects with significant unknowns or experimental construction methods.
Option C: 18% to 25%
2% to 4% is too low for a commercial construction project of this magnitude. This minimal contingency would not adequately cover typical unforeseen conditions, change orders, or material cost escalations that commonly occur in commercial construction.
Memory Technique
Use 'FIVE to TEN' rule: Commercial projects need 5% to 10% contingency - remember 'Commercial = 5-10, like counting on your fingers (5) to your toes (10)'
Reference Hint
Florida Building Code Chapter 1, Section 107 (Construction Documents) and construction estimating references in the Business and Finance Law study materials
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
According to quality control standards, concrete cylinder tests show compressive strength of 2,800 psi when the specification requires 3,000 psi. What should the contractor do?
Next Question
A building permit fee calculation includes a base fee of $125 plus $0.75 per square foot for a 4,200 square foot residence. Additionally, there is a 3% processing fee on the total. What is the final permit cost?
