According to B&P Code 7159.5, service and repair contracts must include specific provisions. Which statement is correct regarding these contracts?

Correct Answer

D) The contract must specify that no work exceeding $750 will be performed without prior written authorization

B&P Code 7159.5(a)(4) requires service and repair contracts to include a statement that no work exceeding $750 in cost will be performed without the prior written authorization of the person contracting for the work.

Answer Options
A
The contractor may begin work immediately without waiting periods
B
Service contracts under $500 are exempt from all disclosure requirements
C
Oral agreements are acceptable for service work under $1,000
D
The contract must specify that no work exceeding $750 will be performed without prior written authorization

Why This Is the Correct Answer

Business and Professions Code Section 7159.5(a)(4) specifically mandates that service and repair contracts must include a clear statement that no work exceeding $750 in cost will be performed without obtaining prior written authorization from the person contracting for the work. This provision protects consumers from unexpected charges and ensures transparency in service work pricing. The $750 threshold is a critical consumer protection measure that contractors must strictly observe.

Why the Other Options Are Wrong

Option A: The contractor may begin work immediately without waiting periods

B&P Code 7159.5 requires service and repair contracts to be in writing and include specific provisions. Oral agreements are not acceptable for service work under $1,000 or any amount. The written contract requirement ensures proper documentation and consumer protection.

Option B: Service contracts under $500 are exempt from all disclosure requirements

Service and repair contracts under B&P Code 7159.5 include specific provisions about timing and authorization. Contractors cannot begin work immediately without following proper procedures, including obtaining written authorization for work exceeding $750 and complying with other contractual requirements.

Memory Technique

Remember '750 Written' - any service work over $750 requires Written authorization before proceeding.

Was this explanation helpful?

More law-business Questions

Under B&P Code Section 7071.9, a contractor may deposit cash or securities instead of obtaining a surety bond. If a contractor chooses this option, where must the deposit be maintained and what happens to interest earned?

Under California's AB 5 law (Dynamex decision), which factor is NOT part of the ABC test for determining independent contractor status?

According to Business and Professions Code Section 7031, what is required when a licensed contractor supervises work performed by unlicensed employees on a construction project?

Under California Building Standards Code Title 24, which entity has the authority to issue building permits for most residential and commercial construction projects?

Which of the following activities is exempt from California contractor licensing requirements under Business and Professions Code Section 7048?

Under Cal/OSHA regulations in Title 8 CCR Section 5192, Safety Data Sheets (SDS) for hazardous chemicals used on construction sites must be readily accessible to employees during which hours?

Under California Business and Professions Code Section 7071.9, in lieu of a surety bond, what alternative security may a contractor provide to satisfy the contractor license bond requirement?

According to Cal/OSHA regulations, which of the following is NOT a required element of a written Injury and Illness Prevention Program (IIPP)?

A homeowner requests that a B-General Building Contractor provide a certificate of insurance naming the homeowner as an additional insured on the contractor's general liability policy. Under California law, what is the contractor's obligation?

Under California Civil Code Section 8816, when a stop payment notice exceeds $1,200 on a private work project, what must the claimant provide to make the notice effective?