During window installation in a concrete block wall, what is the most critical step to prevent water infiltration?
Correct Answer
B) Properly flashing the sill and head
Proper flashing installation, especially at the sill and head, is critical for preventing water infiltration. Flashing directs water away from the window opening and is the primary defense against water penetration.
Why This Is the Correct Answer
Proper flashing installation at the sill and head is the most critical step because it creates the primary water barrier system that directs water away from the window opening. Flashing acts as the first line of defense against water infiltration by channeling water to the exterior before it can penetrate the wall assembly. Without proper flashing, even perfectly installed windows will eventually fail due to water penetration, making this the most fundamental requirement for long-term water resistance.
Why the Other Options Are Wrong
Option A: Installing the window level and plumb
While installing the window level and plumb is important for proper operation and appearance, it does not directly address water infiltration prevention. A window can be perfectly level and plumb but still allow water penetration without proper flashing.
Option C: Using expanding foam around the frame
Expanding foam is primarily used for air sealing and thermal insulation around the frame, not as a primary water barrier. Foam can actually trap water if infiltration occurs and should never be relied upon as the main defense against water penetration.
Option D: Caulking the interior perimeter
Interior caulking is a secondary measure that addresses air infiltration and provides a finished appearance, but it does not prevent water from entering the wall assembly. Water infiltration must be stopped at the exterior, not managed from the interior.
More Project Mgmt Questions
What is the minimum R-value required for wall insulation in Florida Climate Zone 2?
A subcontractor brings a new chemical product to your jobsite. Under the Globally Harmonized System (GHS), what information must be immediately available to workers?
A construction site has a trench that is 8 feet deep in Type B soil. What is the maximum allowable slope ratio for the trench walls without protective systems?
A detail drawing shows a scale of 3/4" = 1'-0". If a dimension measures 2.25 inches on the drawing, what is the actual dimension?
What is the maximum recommended spacing between drywall screws when attaching to wood studs?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Previous Question
A mobile crane is lifting a 15,000-pound load at a 60-foot radius. The crane's load chart shows a capacity of 18,000 pounds at this radius. What is the actual safety margin for this lift?
Next Question
What is the primary advantage of using Insulated Concrete Forms (ICF) in construction?