EstatePass
Contract AdminContractsmedium40% of exam part

During final closeout, the architect identifies $12,000 worth of punch list items. The contract retainage held is $45,000. The owner wants to release $30,000 of retainage and hold $15,000 pending completion of punch list work. Is this approach reasonable?

Correct Answer

C) Yes, this provides reasonable security while releasing most funds

Holding $15,000 against $12,000 of punch list work provides reasonable security for the owner while releasing the majority of retainage funds. This approach balances the owner's protection with the contractor's cash flow needs.

Answer Options
A
No, all retainage must be held until punch list completion
B
No, retainage can only be released after final completion
C
Yes, this provides reasonable security while releasing most funds
D
Yes, but only if the contractor agrees in writing

Why This Is the Correct Answer

CORRECT_ANSWER - This approach is reasonable because it provides adequate security for the owner while improving the contractor's cash flow. Holding $15,000 against $12,000 of punch list work gives the owner a 125% security margin, which is more than sufficient to cover the remaining work. The practice of partial retainage release during closeout is common and beneficial when properly managed with appropriate security ratios.

Why the Other Options Are Wrong

Option A: No, all retainage must be held until punch list completion

This is overly restrictive and not required by law or standard practice. Holding all retainage until punch list completion unnecessarily restricts contractor cash flow when adequate security can be maintained with a smaller amount.

Option B: No, retainage can only be released after final completion

While retainage is typically held until final completion, partial release during closeout is acceptable when sufficient security remains. This rigid interpretation doesn't account for reasonable business practices that balance owner protection with contractor cash flow needs.

Option D: Yes, but only if the contractor agrees in writing

While contractor agreement is always preferable, it's not legally required for the owner to make this reasonable adjustment to retainage release. The owner has the right to manage retainage releases as long as they maintain adequate security for remaining work.

Memory Technique

Remember 'R.S.R.' - Reasonable Security Ratio. As long as retainage held exceeds remaining work value by 10-50%, partial release is typically acceptable.

Reference Hint

Florida Building Code Chapter 1, Section 713 (Lien Law) and AIA A201 General Conditions regarding retainage and substantial completion procedures

More Contract Admin Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing