During construction, you discover that the structural steel inspection was failed due to improper welding. What is the required next step before proceeding with work?
Correct Answer
B) Correct the deficiency and request a re-inspection
When an inspection fails, the deficiency must be corrected and a re-inspection requested before any subsequent work can proceed. This ensures compliance with approved plans and codes.
Why This Is the Correct Answer
When any inspection fails, Florida Building Code requires that all deficiencies be corrected before work can continue. The contractor must fix the improper welding, then request a re-inspection from the building department to verify compliance. Only after the re-inspection passes can subsequent construction work proceed. This process ensures structural integrity and code compliance throughout the construction process.
Why the Other Options Are Wrong
Option A: Continue work and address the issue at final inspection
Continuing work after a failed inspection violates Florida Building Code requirements and could result in stop-work orders, fines, and potential safety hazards. All failed inspections must be addressed immediately.
Option C: Submit a variance request to the building department
A variance request is used for seeking approval to deviate from code requirements before construction, not to address failed inspections. Structural welding deficiencies cannot be resolved through variance requests.
Option D: Have the architect approve the existing work
The architect does not have authority to override building code requirements or approve failed inspections. Only the building official can approve inspections after deficiencies are corrected.
Memory Technique
Use 'SFR' - Stop work, Fix deficiency, Request re-inspection. Think 'Safety First Rule' to remember the sequence.
Reference Hint
Florida Building Code Chapter 1, Section 110 - Inspections and Tests
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Previous Question
What is the primary difference between a contingency and an allowance in construction estimating?
Next Question
A project requires 2,400 square feet of drywall installation. If a crew can install 300 square feet per day at a labor cost of $45 per hour for 8-hour days, what is the total labor cost for drywall installation?