During construction, the architect requests that the HVAC ductwork be relocated 3 feet to the east from the original design. What documentation should be prepared?
Correct Answer
B) As-built drawings showing the new location
As-built drawings must be prepared to document the actual installed location of the ductwork, which differs from the original design. This ensures accurate records for future maintenance and modifications.
Why This Is the Correct Answer
As-built drawings are the primary documentation required when actual construction deviates from the original design plans. These drawings record the exact location and configuration of installed systems as they were actually built, not as originally designed. For HVAC ductwork relocation, as-built drawings ensure that future maintenance, repairs, or modifications can be performed accurately since technicians will know the true location of the ductwork. This documentation is essential for building operations and is typically required by building codes and professional standards.
Why the Other Options Are Wrong
Option A: A change order only
While a change order may be needed for cost and contract modifications, it doesn't provide the technical documentation of where the ductwork was actually installed. Change orders address contractual and financial aspects but don't serve as construction records.
Option C: A revised construction schedule
A revised construction schedule addresses timing and sequencing of work but doesn't document the physical location changes of the installed ductwork. Schedule updates don't provide the spatial documentation needed for future reference.
Option D: An updated material list
An updated material list might be needed if different materials are required, but it doesn't document the actual installed location of the ductwork. Material lists address quantities and specifications, not spatial positioning.
Memory Technique
Think 'AS-BUILT = AS it was ACTUALLY BUILT' - whenever actual construction differs from plans, as-built drawings document reality.
Reference Hint
Florida Building Code, Chapter 1, Section 107 (Submittal Documents) and AIA Contract Documents regarding as-built drawing requirements
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Previous Question
A building permit application is submitted with a construction value of $850,000. The plan review fee is 65% of the building permit fee, and the permit fee is $12 per $1,000 of construction value. What is the total amount due for permit and plan review fees?
Next Question
An owner requests a change that will add $35,000 to the contract price and 12 days to the schedule. The contractor's markup on changes is 15% for overhead and profit. What should be the total change order amount?