EstatePass
Contract AdminPermitsmedium20% of exam part

During construction of a single-family home, you discover that the footing inspection was failed due to inadequate concrete coverage over rebar. What is the most appropriate next step?

Correct Answer

B) Correct the deficiency and request a re-inspection

When an inspection fails, work must stop in that area and the deficiency must be corrected before proceeding. A re-inspection must be requested and passed before continuing to the next phase of construction.

Answer Options
A
Continue with construction and address the issue later
B
Correct the deficiency and request a re-inspection
C
Pour the foundation slab and schedule the next inspection
D
Contact the engineer to modify the plans

Why This Is the Correct Answer

When any inspection fails, Florida Building Code requires that work must immediately stop in the affected area and the deficiency must be corrected before any additional work can proceed. The contractor must fix the inadequate concrete coverage over the rebar and then request a re-inspection from the building department. Only after the re-inspection passes can construction continue to the next phase, ensuring structural integrity and code compliance.

Why the Other Options Are Wrong

Option A: Continue with construction and address the issue later

Continuing construction after a failed inspection violates Florida Building Code and can result in serious penalties, stop-work orders, and potential structural safety issues. All deficiencies must be corrected immediately.

Option C: Pour the foundation slab and schedule the next inspection

Proceeding to pour the foundation slab before correcting the failed footing inspection would compound the violation and potentially create serious structural problems. The footing must pass inspection first.

Option D: Contact the engineer to modify the plans

While an engineer might need to be consulted in some cases, the primary issue here is inadequate concrete coverage, which is typically a construction execution problem rather than a design issue requiring plan modifications.

Memory Technique

Use the acronym 'SFR' - Stop work, Fix the problem, Request re-inspection. Think 'Single Family Residence' to remember the sequence for any failed inspection.

Reference Hint

Florida Building Code Chapter 1, Section 110 - Inspections; also reference the specific concrete coverage requirements in ACI 318 as adopted by Florida Building Code

More Contract Admin Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing