EstatePass
Contract AdminPermitsmedium20% of exam part

During construction of a residential home, the contractor fails to schedule the required rough electrical inspection before covering the wiring. What is the most likely consequence?

Correct Answer

B) Work must stop until the inspection is completed and approved

When required inspections are missed before work is covered, construction must stop until the area is exposed for proper inspection and approval. This ensures compliance with building codes and safety standards.

Answer Options
A
The contractor will receive a warning but can proceed
B
Work must stop until the inspection is completed and approved
C
The contractor must pay a double inspection fee
D
The final inspection will cover all missed inspections

Why This Is the Correct Answer

Florida building codes require specific inspections at designated stages before work can be covered or proceed to the next phase. When a contractor fails to schedule a required rough electrical inspection before covering the wiring, all work must cease until the covered area is exposed for proper inspection. This is a mandatory stop-work situation because electrical systems pose significant safety risks and must be verified for code compliance before being concealed. The building department has the authority to halt construction until proper inspections are completed and approved.

Why the Other Options Are Wrong

Option A: The contractor will receive a warning but can proceed

Final inspections cannot retroactively cover missed rough inspections because the electrical work is now concealed and cannot be properly evaluated for code compliance and safety without exposure.

Option C: The contractor must pay a double inspection fee

While some jurisdictions may impose additional fees for re-inspections or violations, the primary consequence is not a double inspection fee but rather the mandatory cessation of work until proper inspection occurs.

Memory Technique

Think 'Cover Before Check = Construction Stops' - if you cover work before the required inspection check, construction must stop completely.

Reference Hint

Florida Building Code Chapter 1, Section 110 - Inspections and Testing requirements

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.