During construction of a LEED project, the contractor discovers that a specified low-VOC paint is not available and wants to substitute a conventional paint. What should the contractor do?
Correct Answer
B) Submit a substitution request with documentation showing the alternative meets LEED requirements
Any material substitutions on LEED projects must be properly documented and approved to ensure LEED requirements are still met. The LEED consultant and design team must review and approve substitutions.
Why This Is the Correct Answer
LEED projects require strict adherence to environmental standards and documentation for certification. Any material substitutions must go through a formal review process to ensure the alternative product still meets the specific LEED credit requirements. The LEED consultant and design team must evaluate whether the substitute material maintains the project's sustainability goals and point targets. Proper documentation is essential for maintaining LEED certification integrity.
Why the Other Options Are Wrong
Option A: Make the substitution without notification since it's a minor change
Making substitutions without notification violates LEED protocol and could jeopardize the entire certification. Even seemingly minor changes can significantly impact LEED points and environmental performance.
Option C: Use the conventional paint and adjust LEED points accordingly
Contractors cannot unilaterally adjust LEED points - this is determined by the LEED consultant and certification body. Using non-compliant materials without approval could result in loss of credits or certification failure.
Option D: Delay the work until the specified paint becomes available
While maintaining specifications is important, delaying work may not be necessary if an equivalent LEED-compliant alternative exists. The proper approach is to seek approved substitutions rather than automatic delays.
Memory Technique
Think 'LEED = LEGAL Documentation' - any changes need legal approval through proper channels
Reference Hint
Florida Building Code Chapter 11 - Special Construction Requirements, and LEED Reference Guide for Building Design and Construction
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?