EstatePass
Project MgmtBlueprintsmedium17% of exam part

During construction, a contractor discovers that the shop drawings for structural steel conflict with the architectural drawings. What should be the contractor's first course of action?

Correct Answer

C) Submit an RFI to the design team for clarification

When conflicts exist between drawings, the contractor should submit a Request for Information (RFI) to the design team for official clarification rather than making assumptions about which drawing takes precedence.

Answer Options
A
Follow the shop drawings since they are more detailed
B
Follow the architectural drawings since they were issued first
C
Submit an RFI to the design team for clarification
D
Use engineering judgment to determine the best solution

Why This Is the Correct Answer

When conflicts exist between different sets of drawings, the contractor must obtain official clarification from the design team through an RFI (Request for Information). This ensures proper documentation of the issue and provides legal protection for the contractor. Making assumptions about which drawing takes precedence could lead to costly errors, rework, and potential liability issues. The RFI process creates a paper trail and ensures the design team takes responsibility for resolving conflicts in their documents.

Why the Other Options Are Wrong

Option A: Follow the shop drawings since they are more detailed

Shop drawings, while detailed, are prepared by subcontractors or suppliers and must be reviewed and approved by the design team. Following shop drawings that conflict with architectural drawings without clarification could result in work that doesn't meet the overall design intent or building code requirements.

Option B: Follow the architectural drawings since they were issued first

The order of issuance doesn't determine precedence when drawings conflict. Architectural drawings may have been issued first, but they could contain errors or may not reflect the most current design intent. Without official clarification, following one set over another is making an assumption that could be costly.

Option D: Use engineering judgment to determine the best solution

Contractors should not use their own engineering judgment to resolve conflicts between design documents unless they are specifically licensed and contracted to provide design services. This approach could result in liability issues and work that doesn't meet the design team's intent or applicable codes.

Memory Technique

Think 'RFI = Risk-Free Insurance' - submitting an RFI protects you from liability when drawings conflict

Reference Hint

AIA A201 General Conditions - Article 3 (Contractor responsibilities) and Article 4 (Administration of the Contract), specifically sections dealing with RFIs and document interpretation

More Project Mgmt Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing