EstatePass
Contract AdminPreconstructionmedium27% of exam part

During bid evaluation, a general contractor receives subcontractor bids of $45,000, $52,000, $48,000, and $71,000 for the same scope. What should be the contractor's primary concern?

Correct Answer

A) Investigate the scope differences and qualifications of the outlying bids

The $71,000 bid is significantly higher and the $45,000 bid is notably lower than the middle range. Both outliers should be investigated for scope differences, qualifications, or potential errors before making a selection.

Answer Options
A
Investigate the scope differences and qualifications of the outlying bids
B
Average all bids for the estimate
C
Reject the highest and lowest bids
D
Automatically select the lowest bid to maximize profit

Why This Is the Correct Answer

Option B is correct because significant variations in subcontractor bids require investigation to ensure fair comparison. The $45,000 bid could indicate missing scope, inferior materials, or errors, while the $71,000 bid might include additional scope or premium services. Professional contractors must verify that all bids cover the same scope and meet project requirements before making decisions. Simply selecting based on price alone without understanding these differences can lead to costly change orders or quality issues.

Why the Other Options Are Wrong

Option B: Average all bids for the estimate

Averaging all bids is not a valid estimating method and doesn't address the underlying issues causing the bid variations. This approach ignores important factors like scope differences, qualifications, and potential errors in the outlying bids.

Option C: Reject the highest and lowest bids

Automatically selecting the lowest bid without investigation is poor practice that can lead to project problems. The lowest bidder may have misunderstood the scope, excluded necessary items, or may not be qualified to perform the work properly.

Option D: Automatically select the lowest bid to maximize profit

Automatically rejecting the highest and lowest bids without investigation could eliminate potentially valid options. The highest bid might include valuable additional scope, and the lowest might be from a qualified contractor offering competitive pricing.

Memory Technique

Remember 'INVESTIGATE OUTLIERS' - when subcontractor bids have significant variations, always investigate before deciding rather than using mathematical shortcuts or automatic selection rules.

Reference Hint

Florida Building Code - Administrative provisions regarding contractor responsibilities and bid evaluation procedures, Chapter 1

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.