During bid evaluation, a contractor finds that all electrical subcontractor bids exclude temporary power costs estimated at $8,500. The selected electrical bid is $67,200. What should be included in the project estimate for electrical work?

Correct Answer

C) $67,200 plus a separate line item for temporary power

The estimate should include the subcontractor bid amount plus a separate line item for the excluded temporary power costs to ensure all electrical work is covered in the project budget.

Answer Options
A
$67,200
B
$75,700
C
$67,200 plus a separate line item for temporary power
D
$58,700

Why This Is the Correct Answer

Option C is correct because proper project estimating requires transparency and completeness in cost tracking. When subcontractor bids exclude specific costs, the general contractor must account for those costs separately to ensure full project coverage. Creating a separate line item for the $8,500 temporary power costs maintains clear cost accountability and ensures nothing is overlooked during project execution. This approach also helps with change order management if temporary power requirements change during construction.

Why the Other Options Are Wrong

Option A: $67,200

Option A only includes the base electrical bid of $67,200 but completely ignores the excluded temporary power costs of $8,500, which would result in an incomplete project estimate and potential cost overruns.

Option B: $75,700

Option B simply adds the temporary power cost to the electrical bid ($67,200 + $8,500 = $75,700) but fails to maintain the important separate line item tracking that distinguishes between the subcontractor's scope and additional contractor responsibilities.

Option D: $58,700

Option D incorrectly subtracts the temporary power cost from the electrical bid ($67,200 - $8,500 = $58,700), which makes no logical sense since temporary power is an additional cost requirement, not a credit or reduction.

Memory Technique

Remember 'SEPARATE the EXCLUDED' - when subs exclude costs, always separate those costs as distinct line items rather than bundling them together for better project cost control.

Reference Hint

Florida Building Construction Standards and Practices - Chapter on Project Estimating and Bid Analysis, or Construction Project Management references covering subcontractor bid evaluation procedures.

More Contract Admin Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing