During a welding inspection, what indicates a proper fillet weld?
Correct Answer
B) Uniform profile with smooth transitions
A proper fillet weld should have a uniform profile with smooth transitions to the base metal. Porosity, undercut, and excessive spatter are all defects that can compromise weld strength and quality.
Why This Is the Correct Answer
A proper fillet weld must have a uniform profile with smooth transitions to the base metal to ensure structural integrity and proper load transfer. The weld face should be slightly convex or flat, with consistent leg sizes and no abrupt changes in geometry. Smooth transitions prevent stress concentrations that could lead to crack initiation and failure. This uniform appearance indicates proper welding technique, correct heat input, and adequate penetration.
Why the Other Options Are Wrong
Option A: Visible porosity throughout the weld
Visible porosity throughout the weld is a serious defect caused by gas entrapment during welding, which creates voids that significantly reduce the effective cross-sectional area and strength of the weld joint.
Option C: Deep undercut along the weld toe
Deep undercut along the weld toe is a defect where the base metal is melted away at the junction, creating a groove that acts as a stress concentrator and reduces the effective throat thickness of the weld.
Option D: Excessive spatter around the weld area
Excessive spatter around the weld area indicates poor welding technique or incorrect parameters, and while spatter itself doesn't affect weld strength, it suggests potential quality issues and creates cleanup problems.
Memory Technique
Think 'SMOOTH SUIT' - a proper weld should be as smooth and uniform as a well-tailored suit, with no bumps, holes, or rough edges.
Reference Hint
AWS D1.1 Structural Welding Code - Steel, Chapter 6 (Inspection) or Florida Building Code Chapter 17 (Structural Tests and Special Inspections)
More Project Mgmt Questions
What is the minimum R-value required for wall insulation in Florida Climate Zone 2?
A subcontractor brings a new chemical product to your jobsite. Under the Globally Harmonized System (GHS), what information must be immediately available to workers?
A construction site has a trench that is 8 feet deep in Type B soil. What is the maximum allowable slope ratio for the trench walls without protective systems?
A detail drawing shows a scale of 3/4" = 1'-0". If a dimension measures 2.25 inches on the drawing, what is the actual dimension?
What is the maximum recommended spacing between drywall screws when attaching to wood studs?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Previous Question
A detail drawing shows a bathroom door with a note stating '32" MIN CLR'. According to ADA requirements, what does this specification ensure?
Next Question
A concrete footing requires 45 cubic yards of concrete. The concrete truck delivers in increments of 10 cubic yards. How many truck loads will be needed?