During a weekly subcontractor coordination meeting, the electrical subcontractor reports they cannot start rough-in work as scheduled because the framing inspection has not been completed. What is the general contractor's BEST immediate response?
Correct Answer
D) Contact the building inspector to expedite the framing inspection
The general contractor should work to remove the obstacle preventing the electrical work by coordinating with the building inspector. This maintains the schedule while ensuring proper inspection sequencing.
Why This Is the Correct Answer
Option D is correct because the general contractor must address the root cause of the delay - the missing framing inspection. Contacting the building inspector to expedite the inspection removes the obstacle preventing electrical rough-in work while maintaining proper inspection sequencing. This proactive approach keeps the project on schedule and ensures compliance with building codes and permit requirements.
Why the Other Options Are Wrong
Option A: Reassign the electrical crew to work on another area of the project
Reassigning the electrical crew to another area is a temporary workaround that doesn't solve the underlying problem. The framing inspection will still be needed eventually, and this approach may create scheduling conflicts later when the crew needs to return to complete the original work.
Option B: Tell the electrical subcontractor to proceed without the inspection
Telling the electrical subcontractor to proceed without inspection violates building codes and permit requirements. This could result in failed inspections, rework, fines, and potential safety hazards. Work must follow proper inspection sequences as mandated by local building authorities.
Option C: Terminate the electrical subcontractor for non-performance
Terminating the electrical subcontractor for non-performance is inappropriate since the delay is not their fault. The subcontractor is correctly following proper procedures by waiting for the required framing inspection before proceeding with rough-in work.
Memory Technique
Remember 'CLEAR THE PATH' - when subcontractors are blocked by missing inspections, the GC must Clear the obstacle by coordinating with inspectors to keep the project moving forward.
More NASCLA Questions
Which AIA document contains the general conditions that govern the rights and responsibilities of all parties in a construction contract?
A construction company has direct labor costs of $85,000, direct materials of $120,000, and overhead costs of $45,000 for a project. What is the total job cost?
What is the primary purpose of job cost accounting in construction?
A construction company has current assets of $350,000 and current liabilities of $280,000. What is the company's working capital?
In CSI MasterFormat, which division covers earthwork and site preparation?
In a mechanical drawing, what does 'CFM' typically measure?
In CSI MasterFormat Division 08, which of the following would typically be included?
On a mechanical plan, what does the symbol 'RTU' typically indicate?
What is the minimum preheat temperature for welding ASTM A992 steel when the ambient temperature is 15Β°F?
A general contractor's balance sheet shows total assets of $850,000, current liabilities of $320,000, and long-term debt of $180,000. What is the company's equity?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A project requires accessible parking spaces for a 150-space parking lot. According to ADA requirements, what is the minimum number of accessible spaces required?
Next Question
On electrical drawings, what does the symbol showing a circle with the letter 'J' inside typically represent?
