During a weekly coordination meeting, the electrical subcontractor reports they cannot install panel boxes because the concrete walls are not ready. What should the general contractor do first?
Correct Answer
B) Review the project schedule and coordinate with concrete subcontractor
The general contractor should first review the schedule to understand the impact and coordinate with the concrete subcontractor to determine the cause of delay and develop a recovery plan. This systematic approach addresses the root cause.
Why This Is the Correct Answer
Option B represents proper project management protocol. The general contractor must first assess the situation by reviewing the project schedule to understand dependencies, critical path impacts, and timeline implications. Then coordinate with the concrete subcontractor to identify the root cause of the delay, whether it's material shortages, labor issues, or other factors. This systematic approach allows for informed decision-making and development of an appropriate recovery plan rather than making hasty decisions without full information.
Why the Other Options Are Wrong
Option A: Hire additional concrete workers immediately
Hiring additional workers immediately is premature without understanding the actual cause of the delay. The issue might be material shortages, design problems, or other factors that additional labor cannot solve. This reactive approach could waste resources and create coordination problems.
Option C: Terminate the concrete subcontractor
Terminating the concrete subcontractor is an extreme measure that should only be considered after investigation and attempts at resolution. This action would likely cause greater delays, legal complications, and additional costs without addressing the underlying problem.
Option D: Tell electrical to wait until next week
Simply telling electrical to wait ignores the project management responsibility to investigate and resolve scheduling conflicts. This passive approach fails to address the delay's impact on the critical path and other trades.
Memory Technique
Remember 'RICA': Review schedule, Investigate cause, Coordinate solution, Act appropriately. Always review before you react.
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass