During a weekly construction coordination meeting, the electrical subcontractor reports they are 3 days behind schedule on a non-critical path activity with 5 days of total float. What should the general contractor's immediate response be?
Correct Answer
B) Document the delay and continue monitoring since float remains available
Since the activity has 5 days of total float and is only 3 days behind, there is still 2 days of float remaining. The delay does not impact the critical path, so documentation and continued monitoring is appropriate.
Why This Is the Correct Answer
Option B is correct because the activity still has remaining float (5 days total float - 3 days delay = 2 days remaining). Since this is a non-critical path activity with available float, the delay does not impact the overall project schedule. The appropriate response is to document the delay for tracking purposes and continue monitoring the situation, as no immediate corrective action is required when float remains available.
Why the Other Options Are Wrong
Option A: Immediately accelerate the electrical work at additional cost
Accelerating work immediately would be premature and costly since there are still 2 days of float remaining. This would unnecessarily increase project costs when the delay hasn't yet impacted the critical path or overall project schedule.
Option C: Terminate the electrical subcontractor for poor performance
Terminating a subcontractor for a 3-day delay on a non-critical activity with available float would be an extreme overreaction. This delay doesn't constitute poor performance warranting termination, especially when it doesn't impact the project completion date.
Option D: Notify the owner of a project delay
Notifying the owner of a project delay would be inappropriate since there is no actual project delay. The activity delay is absorbed by the available float, so the overall project schedule remains unchanged.
Memory Technique
Use 'FLOAT = FREEDOM': As long as you have float remaining, you have the freedom to absorb delays without impacting the project completion date.
Reference Hint
Project Management/CPM Scheduling chapter - look for sections on 'Float' or 'Total Float' and 'Critical Path Method'
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Previous Question
An owner specifies liquidated damages of $2,000 per day for a $500,000 project with a 100-day schedule. The actual damages from delay are estimated at $800 per day. What is the likely enforceability of this clause?
Next Question
Which of the following is a key agenda item for effective construction coordination meetings?