EstatePass
Contract AdminProceduresmedium13% of exam part

During a weekly construction coordination meeting, the electrical subcontractor reports they cannot install outlet boxes until the framing inspection is complete. What should the general contractor do first?

Correct Answer

D) Coordinate with the building department to expedite the framing inspection

The general contractor should first coordinate with the building department to expedite the required inspection, as this removes the constraint blocking the electrical work and keeps the project on schedule.

Answer Options
A
Tell the electrical contractor to proceed anyway to stay on schedule
B
Reassign the electrical crew to work on another area of the project
C
Cancel all subsequent trades until electrical work is complete
D
Coordinate with the building department to expedite the framing inspection

Why This Is the Correct Answer

Coordinating with the building department to expedite the framing inspection is the correct first step because it directly addresses the root cause of the delay. The electrical contractor cannot legally proceed without the required inspection approval. By working with the building department to schedule or expedite the inspection, the general contractor removes the constraint blocking electrical work while maintaining compliance with building codes and keeping the project on schedule.

Why the Other Options Are Wrong

Option A: Tell the electrical contractor to proceed anyway to stay on schedule

Canceling all subsequent trades creates unnecessary project delays and cost overruns. Many other trades can continue working in areas not dependent on electrical rough-in. This extreme response would halt productivity across the entire project when only one specific constraint needs resolution.

Option B: Reassign the electrical crew to work on another area of the project

Telling the electrical contractor to proceed without the required framing inspection violates building codes and permit requirements. This could result in failed inspections, work stoppage orders, fines, and potential safety hazards. The work would likely need to be redone after proper inspection.

Option C: Cancel all subsequent trades until electrical work is complete

While reassigning the electrical crew might seem logical, it doesn't solve the underlying problem. The framing inspection will still be needed before any electrical outlet boxes can be installed anywhere in the project. This approach delays addressing the real issue and may create scheduling conflicts later.

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.