EstatePass
Contract AdminPermitsmedium20% of exam part

During a rough-in inspection, the building inspector finds several code violations. What is the contractor's next required action?

Correct Answer

B) Correct the violations and request a re-inspection

When violations are found during any inspection, the contractor must correct all violations and request a re-inspection before proceeding to the next phase of construction. Work cannot continue until the inspection passes.

Answer Options
A
Schedule the next inspection immediately
B
Correct the violations and request a re-inspection
C
Appeal the inspector's decision to the building department
D
Continue with the project and address violations at final inspection

Why This Is the Correct Answer

Option B is correct because Florida Building Code requires that all violations found during inspections must be corrected before work can proceed to the next phase. The contractor cannot continue construction until the inspector approves the corrected work through a re-inspection. This ensures safety standards are met and prevents defective work from being concealed by subsequent construction phases. The inspection process is sequential and each phase must pass before moving forward.

Why the Other Options Are Wrong

Option A: Schedule the next inspection immediately

Scheduling the next inspection without correcting violations is premature and violates code requirements. The inspector will not approve the next phase until current violations are resolved.

Option C: Appeal the inspector's decision to the building department

Appeals are only appropriate when there's a legitimate dispute about code interpretation, not when clear violations exist. Appeals also take time and don't allow work to continue, making this an inefficient first step.

Option D: Continue with the project and address violations at final inspection

Continuing work with unresolved violations violates building codes and can result in stop-work orders, fines, and potential safety hazards. Violations must be corrected immediately, not deferred to final inspection.

Memory Technique

Use the acronym 'CFR' - Correct violations, Fix problems, Request re-inspection. Think 'Code of Federal Regulations' to remember the order.

Reference Hint

Florida Building Code Chapter 1 - Administration and Enforcement, Section on Inspections and Approvals

More Contract Admin Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing