During a coordination meeting, the HVAC contractor states they need 2 additional days to complete ductwork, which will delay the drywall contractor. The project is already behind schedule. What is the best course of action?
Correct Answer
B) Evaluate options including overlapping work, additional crews, or schedule adjustments
The general contractor should evaluate all available options including work sequencing changes, additional resources, or controlled schedule adjustments to minimize project impact while maintaining quality and safety.
Why This Is the Correct Answer
Option B demonstrates proper project management by requiring the general contractor to thoroughly analyze all available solutions before making decisions. This approach considers multiple variables including cost, schedule impact, quality, and safety while exploring creative solutions like work sequencing changes or resource adjustments. A comprehensive evaluation ensures the best possible outcome for the project rather than making hasty decisions that could create additional problems. This methodical approach is essential for effective construction management and minimizes overall project risk.
Why the Other Options Are Wrong
Option A: Tell the HVAC contractor to work overtime to maintain the original schedule
Mandating overtime without evaluation may increase costs unnecessarily, could lead to worker fatigue and safety issues, and doesn't consider if overtime will actually solve the scheduling conflict or if other solutions might be more effective.
Option C: Delay the drywall work and accept the schedule impact
Simply accepting the delay without exploring alternatives is poor project management and could unnecessarily extend the project timeline and increase costs when better solutions might be available.
Option D: Start drywall work around the incomplete HVAC work
Starting drywall around incomplete HVAC work creates safety hazards, quality issues, and will likely require rework when HVAC installation is completed, ultimately costing more time and money.
Memory Technique
Think 'EVALUATE before you EXECUTE' - always analyze all options before making project decisions.
Reference Hint
Florida Building Code Chapter 1, Construction Administration and Project Management sections
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Previous Question
A concrete pour is scheduled for tomorrow, but the quality control checklist shows that rebar inspection has not been completed. The concrete supplier cannot reschedule without significant cost. What should the general contractor do?
Next Question
A contract includes liquidated damages of $1,000 per day with a maximum cap of $50,000. The project is 75 days late due to contractor delays. What is the total liquidated damages assessment?