EstatePass
Contract AdminProceduresmedium13% of exam part

During a coordination meeting, the HVAC and electrical trades report a conflict where their work overlaps in the same ceiling space. What is the most appropriate first step to resolve this conflict?

Correct Answer

C) Review the contract documents and coordination drawings to determine priority

The first step should be to review contract documents, specifications, and coordination drawings to determine if there are established priorities or coordination requirements that address the conflict.

Answer Options
A
Have the trades work it out between themselves
B
Award the space to whichever trade has the earlier start date
C
Review the contract documents and coordination drawings to determine priority
D
Redesign the entire ceiling layout

Why This Is the Correct Answer

Reviewing contract documents and coordination drawings is the proper first step because these documents establish the legal framework and technical requirements for the project. They often contain specific provisions for trade coordination, priority systems, and conflict resolution procedures. This systematic approach ensures decisions are based on contractual obligations rather than arbitrary choices, and it protects the contractor from potential liability issues.

Why the Other Options Are Wrong

Option A: Have the trades work it out between themselves

Having trades work it out themselves abdicates the general contractor's responsibility for coordination and could lead to delays, disputes, or suboptimal solutions that don't consider the overall project requirements.

Option B: Award the space to whichever trade has the earlier start date

Awarding space based on start dates is arbitrary and doesn't consider technical requirements, code compliance, or contractual priorities that may supersede scheduling considerations.

Option D: Redesign the entire ceiling layout

Redesigning the entire ceiling layout is premature and costly without first checking if existing contract documents already provide a solution to the conflict.

Memory Technique

Think 'CCD First' - Check Contract Documents first before making coordination decisions.

Reference Hint

Florida Building Code Chapter 1 - Administration and Enforcement, and AIA A201 General Conditions Article 3 - Contractor responsibilities for coordination

More Contract Admin Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing