During a coordination meeting, it's discovered that the electrical rough-in conflicts with plumbing runs in the same wall cavity. Who should resolve this conflict?
Correct Answer
C) The general contractor in coordination with the architect/engineer
The general contractor is responsible for overall project coordination and should work with the architect/engineer to resolve trade conflicts. This ensures the solution meets design intent and code requirements while maintaining project schedule.
Why This Is the Correct Answer
The general contractor has overall responsibility for project coordination and trade management. When conflicts arise between trades, the GC must work with the design team (architect/engineer) to ensure any resolution maintains structural integrity, meets code requirements, and preserves design intent. This collaborative approach ensures the solution is properly engineered and documented rather than leaving subcontractors to make potentially problematic field decisions.
Why the Other Options Are Wrong
Option A: The electrical subcontractor
While the electrical subcontractor is involved in the conflict, they cannot unilaterally decide how to resolve it. They lack authority over other trades and may not have the expertise to ensure their solution doesn't compromise structural, mechanical, or design requirements.
Option B: The plumbing subcontractor
The plumbing subcontractor, like the electrical contractor, is only one party in the conflict and cannot make decisions that affect other trades or structural elements. They also lack the authority to modify design elements or coordinate with other disciplines.
Option D: The building inspector
Building inspectors enforce code compliance but are not responsible for resolving design conflicts or coordinating construction activities. Their role is regulatory oversight, not project management or design problem-solving.
Memory Technique
Think 'GC + A/E = Solution' - General Contractor plus Architect/Engineer equals proper conflict resolution. The GC coordinates, the design team validates.
Reference Hint
Florida Building Code, Chapter 1 - Scope and Administration, and project management sections dealing with contractor responsibilities and coordination
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Previous Question
According to AIA Document A201, when must the contractor provide written notice to the architect of any claim for additional time or money?
Next Question
A contractor owns a bulldozer that cost $180,000 new, has a useful life of 8 years, and an estimated salvage value of $36,000. Using straight-line depreciation, what is the hourly ownership cost if the machine operates 1,500 hours per year?