EstatePass
Contract AdminProceduresmedium13% of exam part

During a coordination meeting, it's discovered that the electrical rough-in conflicts with plumbing runs in the same wall cavity. Who should resolve this conflict?

Correct Answer

C) The general contractor in coordination with the architect/engineer

The general contractor is responsible for overall project coordination and should work with the architect/engineer to resolve trade conflicts. This ensures the solution meets design intent and code requirements while maintaining project schedule.

Answer Options
A
The electrical subcontractor
B
The plumbing subcontractor
C
The general contractor in coordination with the architect/engineer
D
The building inspector

Why This Is the Correct Answer

The general contractor has overall responsibility for project coordination and trade management. When conflicts arise between trades, the GC must work with the design team (architect/engineer) to ensure any resolution maintains structural integrity, meets code requirements, and preserves design intent. This collaborative approach ensures the solution is properly engineered and documented rather than leaving subcontractors to make potentially problematic field decisions.

Why the Other Options Are Wrong

Option A: The electrical subcontractor

While the electrical subcontractor is involved in the conflict, they cannot unilaterally decide how to resolve it. They lack authority over other trades and may not have the expertise to ensure their solution doesn't compromise structural, mechanical, or design requirements.

Option B: The plumbing subcontractor

The plumbing subcontractor, like the electrical contractor, is only one party in the conflict and cannot make decisions that affect other trades or structural elements. They also lack the authority to modify design elements or coordinate with other disciplines.

Option D: The building inspector

Building inspectors enforce code compliance but are not responsible for resolving design conflicts or coordinating construction activities. Their role is regulatory oversight, not project management or design problem-solving.

Memory Technique

Think 'GC + A/E = Solution' - General Contractor plus Architect/Engineer equals proper conflict resolution. The GC coordinates, the design team validates.

Reference Hint

Florida Building Code, Chapter 1 - Scope and Administration, and project management sections dealing with contractor responsibilities and coordination

More Contract Admin Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing