During a construction coordination meeting, the electrical subcontractor reports they cannot install panels until the drywall is complete, but the drywall contractor needs electrical rough-in first. What should the general contractor do?
Correct Answer
B) Clarify the proper sequence and coordinate the schedule
The general contractor should clarify the proper construction sequence (electrical rough-in before drywall, electrical panels after drywall) and coordinate the schedule accordingly. This prevents conflicts and ensures proper work flow.
Why This Is the Correct Answer
Option B is correct because the general contractor's primary responsibility is project coordination and scheduling. The GC must understand that electrical work occurs in two phases: rough-in (before drywall) and finish work including panels (after drywall). By clarifying the proper sequence and coordinating the schedule, the GC ensures both trades can work efficiently without conflicts. This demonstrates proper project management and prevents costly delays or rework.
Why the Other Options Are Wrong
Option A: Tell the electrical contractor to work around the drywall
This option ignores proper construction sequencing and could result in code violations, safety issues, and poor workmanship. Electrical panels cannot be properly installed without access behind walls, and forcing trades to work around each other creates inefficiency and potential conflicts.
Option C: Delay both trades until the issue resolves itself
Passive delay without action fails the GC's duty to actively manage and coordinate the project. This approach wastes time, increases costs, and doesn't address the underlying scheduling confusion that caused the conflict.
Option D: Hire additional workers to speed up both trades
Adding workers doesn't solve the sequencing problem and may actually create more confusion on the jobsite. The issue is coordination and scheduling, not labor shortage, so this solution addresses the wrong problem.
Memory Technique
Think 'ROUGH before ROCK' - electrical rough-in comes before drywall (sheetrock), then electrical finish work comes after drywall is complete
Reference Hint
Florida Building Code Chapter 1, Project Management and Coordination sections, or Construction Management reference materials covering trade sequencing
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Previous Question
A complex project has multiple critical paths with durations of 180, 185, and 190 days respectively. The project experiences a 3-day delay on the path with 185-day duration. What is the new project duration?
Next Question
In a cost-plus-fee contract, the contractor is reimbursed for all legitimate project costs plus a predetermined fee. What is the primary risk for the owner in this contract type?