EstatePass
Contract AdminProceduresmedium13% of exam part

During a construction coordination meeting, the electrical subcontractor reports they cannot install panels until the drywall is complete, but the drywall contractor needs electrical rough-in first. What should the general contractor do?

Correct Answer

B) Clarify the proper sequence and coordinate the schedule

The general contractor should clarify the proper construction sequence (electrical rough-in before drywall, electrical panels after drywall) and coordinate the schedule accordingly. This prevents conflicts and ensures proper work flow.

Answer Options
A
Tell the electrical contractor to work around the drywall
B
Clarify the proper sequence and coordinate the schedule
C
Delay both trades until the issue resolves itself
D
Hire additional workers to speed up both trades

Why This Is the Correct Answer

Option B is correct because the general contractor's primary responsibility is project coordination and scheduling. The GC must understand that electrical work occurs in two phases: rough-in (before drywall) and finish work including panels (after drywall). By clarifying the proper sequence and coordinating the schedule, the GC ensures both trades can work efficiently without conflicts. This demonstrates proper project management and prevents costly delays or rework.

Why the Other Options Are Wrong

Option A: Tell the electrical contractor to work around the drywall

This option ignores proper construction sequencing and could result in code violations, safety issues, and poor workmanship. Electrical panels cannot be properly installed without access behind walls, and forcing trades to work around each other creates inefficiency and potential conflicts.

Option C: Delay both trades until the issue resolves itself

Passive delay without action fails the GC's duty to actively manage and coordinate the project. This approach wastes time, increases costs, and doesn't address the underlying scheduling confusion that caused the conflict.

Option D: Hire additional workers to speed up both trades

Adding workers doesn't solve the sequencing problem and may actually create more confusion on the jobsite. The issue is coordination and scheduling, not labor shortage, so this solution addresses the wrong problem.

Memory Technique

Think 'ROUGH before ROCK' - electrical rough-in comes before drywall (sheetrock), then electrical finish work comes after drywall is complete

Reference Hint

Florida Building Code Chapter 1, Project Management and Coordination sections, or Construction Management reference materials covering trade sequencing

More Contract Admin Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing